Annual Permit Performance Report

 

 

In 2023, the Washington State Legislature passed SB 5290, which amends the Local Project Review Act (RCW 36.70B). Its purpose is to consolidate, streamline, and improve the local permit review process, particularly for residential development. Among other amendments, SB 5290 created new requirements for certain jurisdictions to submit annual reports on review processing timelines to the Washington State Department of Commerce. Below is a summary of the annual permit performance data submitted by the City of Camas to the Department of Commerce.

Permit Performance Summary for 2025

  • Preliminary Subdivision Permits: Nine decisions were issued. Eight of those were issued under a consolidated review process. No review exceeded the deadline.
  • Final Subdivision Permits: None
  • Binding Site Plan Permits: None
  • Multifamily Housing Permits: None
  • Construction Permits: Seven civil construction permits were approved. These permits were not reviewed under a consolidated process. No review exceeded the deadline.

Permit Performance Summary for 2024

  • Preliminary Subdivision Permits: None
  • Final Subdivision Permits: Six final plat decisions were issued under a consolidated review process.
  • Binding Site Plan Permits: None
  • Multifamily Housing Permits: One multifamily housing permit was issued.
  • Construction Permits: Seventy-two construction (vertical construction) permits were approved/issued. Nine civil construction permits were approved. Permits were not reviewed under a consolidated process. No review exceeded the deadline.

Annual Permit Performance Summary Report Table

Permit Type Total number of decisions Number of permits reviewed under a consolidated process Number of permits reviewed separately Average calendar days to process (without pauses) Average calendar days of review (with pauses) Number of decisions exceeding the deadline
2024 2025 2024 2025 2024 2025 2024 2025 2024 2025 2024 2025
Preliminary Subdivision 0 9 0 8 0 1 0 28 0 0 0 0
Final Subdivision 6 0 6 0 0 0 0 0 0 0 0 0
Binding Site Plan 0 0 0 0 0 0 0 0 0 0 0 0
Multifamily Housing Permit 1 0 0 0 1 0 140 0 100 0 0 0
Construction Permit 81* 7 0 0 81* 7 53* 38 35* 0 0 0
Total 88 16 6 8 82 8 54 37 36 0 0 0

*The 2024 numbers included building (vertical construction) permits. The 2025 report does not include any vertical construction permits.