Load Full Menu
At its March 16 regular meeting, Camas City Council awarded a $5,269,500 contract to Clark and Sons Excavating of Battle Ground, Wash., for the construction of a roundabout at the intersection of Northeast Lake Road and Northeast Everett Street (State Route 500). The low bid submitted by Clark and Sons Excavating came in approximately $435,000 under the estimated total.
“We are very pleased to have Clark and Sons Excavating working on this important project and thank all the contractors who took the time to submit bids,” said Jim Hodges, City of Camas Project Manager. “We would also like to thank everyone who attended community forums, completed project surveys and provided such valuable feedback.”
With the contract now in place, construction is anticipated to begin in late March or early April 2020 as planned. The roundabout is expected to be functional by early September 2020. At the start of construction, several trees will be removed, as discussed extensively with the public during the planning phase.
The public is encouraged to check the dedicated webpage, www.cityofcamas.us/lakeroadconstruction, over the duration of the project for up-to-date traffic impacts and schedule changes, including those related to any relevant COVID-19 advisories.
 

The construction contract represents about 70% of the total project cost. Making up the other roughly 30% of the total cost is approximately $1,200,000 for design and permitting during the preconstruction phase, which wrapped up last month, $758,000 for construction consultant support and an estimated $250,000 for utility relocations and miscellaneous costs.

Available funding for this project includes approximately $2,830,000 in grant funds from the Transportation Improvement Board (TIB), $4,700,000 in low-interest loans from the Public Works Trust Fund and water utility funds of $600,000. The TIB grant amount, which was originally awarded to the City at $3,300,000, was slightly reduced as a result of the low bids submitted by the contractors and will vary based on actual construction costs.

The city has confirmed that all funding from state agencies is still in place and ready for use. Additionally, city staff are closely monitoring the current public health situation and are following the guidance of lead agencies to ensure the safety and well-being of all staff, contractors and residents.

Camas Public Works News

Public Works Administration
616 NE 4th Avenue
Camas, WA  98607
360.817.1563

Operations Center
1620 SE 8th Avenue
Camas, WA  98607

Engineering
360.817.1561

Inspection Line
(to request an inspection)
360.834.8860

Sanitation
360.817.1564
hotline 360.817.1531

Street Department
360.817.1565

Water & Sewer
360.817.1567
For utility payments
or changes to accounts
360.834.2462

Waste Water Treatment Plant
1129 SE Polk Street
360.834.3263

After Hours Utility Emergencies
360.737.0592

Illicit Discharges (IDDE) Hotline
360.817.1565

Ecology
360.407.6300

My Camas
Go to top